December 6 Update

Anticipated road closures for the remainder of the week are expected to be: Tuesday: Broad Street will be closed between Front Street and White Street and between Monmouth St and Peters Place. Monmouth Street will Read more…

December 3 Update: 12/6-12/10 Schedule

The construction schedule for the week of December 6th can by found by clicking the following link: https://tinyurl.com/Dec6-10Schedule The contractor is adding a second crew so there should be a doubling of activity from prior weeks.  Here Read more…

December 2 Update from RedBankGreen.com

Water Service Issues This Red Bank Green article provides a good summary of the issue regarding water services on Broad Street.  RiverCenter is currently formulating a policy on this issue that we expect to finalize next Read more…

November 24, 2021 Update

The construction will cease prior to Thanksgiving weekend and will resume on Monday, November 29. Next Week’s Schedule: 11/29-11/30 (Mon-Tues):  Continued work on sanitary sewer pipe/manhole between Front and Mechanic Streets. 12/1-12/2 (Wed-Thurs) Sanitary sewer Read more…

November 19, 2021 Update

Broad Street Construction Update — 11/19/2021 Last week the main sanitary sewer and manholes were replaced at all primary Broad Street intersections. This work was conducted at night to avoid closure. Scheduled for next week Read more…

November 15, 2021 Update

November 15th update This week’s work covers the following intersections: 11/5: Front and Broad Street 11/16- 11/18: Harding/Reckless and Broad Street 11/18: Monmouth and Broad Street Most of this week’s construction will be completed at Read more…