November 8, 2021 Update

Published by RiverCenter Staff on

November 8th Update

Right on schedule, the work began on Broad Street this morning.   Crews from Montana Construction are currently working on the waterline between Front Street and Mechanic Street.  The sidewalks and both travel lanes are open in the work area.  The on-street parking spaces are currently closed down in the one-block area.  A construction staging area has been established on a relatively small portion of the eastside parking lots. 

Please make sure to look at the full updated schedule (available here)

Between now and the end of January various underground utilities will be replaced and updated.  The project will then shut down for a couple months and resume in the spring with some sidewalk work, repaving, and restriping to finish the project.

Categories: Updates