November 19, 2021 Update

Published by RiverCenter Staff on

Broad Street Construction Update — 11/19/2021

Last week the main sanitary sewer and manholes were replaced at all primary Broad Street intersections. This work was conducted at night to avoid closure.

Scheduled for next week is:

  • Nov 22-23 (Mon/Tues): The sanitary sewer line is being replaced between Front and Mechanic Streets
  • Nov 24 (Wed): Various storm sewer inlets will be worked on between Front and Linden Streets

No work is scheduled for Thanksgiving Weekend (11/25-11/28.) All construction is to be cleaned up for the Holiday Weekend. All construction vehicles will be moved to the East Side lots.

Have a fantastic Thanksgiving!

Categories: Updates