February 4 Update

Published by Jamie on

The schedule for the week of February 7th can be accessed by clicking the link below:

Upcoming Schedule: https://tinyurl.com/ScheduleFeb7

Most of the major work is focused on Canal Street with an associated road closure and temporary water shutoff.  Affected owners and tenants will be notified separately of any water shuttoffs that affect them. 

We anticipate saw cutting of pavement on Broad Street to begin throughout the project area with short term road closures.  The actual replacement of the water main and individual services should begin either the week of February 14th or 21st, depending upon weather and the ability to get supplies. 

Categories: Updates