The schedule for the week of February 21 can be found by clicking the following link: https://tinyurl.com/Feb21Schedule

There is no construction planned for Monday, February 21. Work will resume on Tuesday, February 22 with the continuation of the water main replacement starting at E. Front and Broad. Saw cutting will also be completed at various locations throughout the week.

Anticipated Road Closures:

Tuesday 2/22 and Wednesday 2/23: Broad Street to be closed between White Street and Front Street. Mechanic Street will be local traffic only.

Thursday 2/24 and Friday 2/25: Broad Street to be closed between White Street and Monmouth Street.