The schedule for the week of April 11th can be found clicking the following link: https://tinyurl.com/ScheduleApril11

ANTICIPATED ROAD CLOSURES:

  • Monday 4/11: Electrical work will be completed in the area of Broad between Front and Mechanic however traffic flow should be maintained in both directions.
  • Tuesday 4/12 and Wednesday 4/13: Trench paving will be completed on Broad Street between Peters and Front Street. Closures are to be expected – exact location and times will be updated early next week.
  • Thursday 4/14 and Friday 4/15: Broad Street will be closed between Front and White Street from approximately 7am-5pm.

SCHEDULED WORK:

Crews will focus on finishing up the tie-ins to the main (Peters and Harding) at the start of the week. Montana group will be notifying properties/businesses in advance if they anticipate any interruption to water service during the process. Electrical work is also scheduled to begin early in the week on Broad between Front and Mechanic. We do anticipate less interruptions to traffic flow during this time.

Trench paving will begin on Tuesday and is expected to be completed on Wednesday. 