Work Schedule: Week of May 16

Published by Jamie on

SCHEDULE: The full schedule for the week of May 16 can be accessed by clicking HERE

ANTICIPATED WORK AND TRAFFIC FLOW:

BROAD STREET: Monday 5/16 through Friday 5/20

  • Curb and sidewalk work will continue between Harding Road and Linden Place.
  • At the beginning of the week, Montana will be concentrating on resetting the remaining pavers on the east side of Broad Street as well as curb work on the northeast corner of Harding Road and Broad Street. Towards the middle to end of the week, curb and sidewalk work will take place on the west side of Broad Street working north.
  • Although parking will be restricted in much of this area, the plan is to utilize lane shifts to keep traffic open in both directions as often as possible. Working hours are approximately 7am-5pm each day. There are no anticipated closures at this time.

SPRING STREET: Monday 5/16 through Friday 5/20

  • Curb and sidewalk work will continue on Spring Street between Harding Road and Towerhill Ave from approximately 7:30am-4pm daily. 

Categories: Updates