Please be advised that next week (July 18th), Montana Construction will begin the process of milling and paving Broad Street from Front Street through Harding Road.

Broad/Harding Detour Map: CLICK HERE

Front Street Detour Map: CLICK HERE

The schedule will be as follows:

  • Monday July 18th: Milling starting south of Front St. and working south on Broad St. towards Harding Rd
    • The following streets will be local traffic only: Mechanic St, White St, Monmouth St (east of Maple), Peter’s Place, Canal St, and Reckless Place
    • The road will be milled in sections and will be reopened as they move south to the extent possible
  • Tuesday July 19th: Paving starting at the Front Street bollards and working South toward Harding Rd
    • Broad St will be closed from Front Street to Leroy Place
    • The following streets will be local traffic only: Mechanic St, White St, Monmouth St (east of Maple), Peter’s Place, Canal St, Reckless Pl, Harding Rd (west of Spring St)
    • The road will be reopened in sections as soon as possible, but will remain closed until safe to drive upon
    • Motorists should expect delays as detours will be in place and plan an alternate route if possible 
  • Wednesday July 20th: Milling and paving the intersection of Broad Street and Front Street, then Canal Street and Hudson Ave
    • Front St will be local traffic only east of Pearl Street and west of Spring St starting at 9AM
    • Broad St will be closed from White Street to Front St starting at 9AM
    • Canal Street will be closed from Broad to Hudson, Clay St will be local traffic only, and Hudson Ave will be closed from Elm Pl to the Linden Lots
    • If there are any delays on Tuesday, paving of the Broad/Harding intersection will take place on Wednesday after the Front St intersection is done.
    • The eastbound ambulance/emergency vehicle route to RMC is Front St to Boatclub Ct to Union St to RMC (highlighted in blue on the detour maps)
    • Motorists should expect delays as detours will be in place and plan an alternate route if possible 
  • Thursday July 21st: Striping and painting of roadway lines, crosswalks, and parking spaces will be completed along the entire project. Minor traffic disruptions will occur but lane shifts will be utilized as much as possible and any road closures will be temporary.  

Working hours are approximately 7AM-4PM each , but hours may be extended in order to complete the paving and stay within the 3 day timeline.